The City of Miami Beach requested proposals from qualified firms to design and build right of way infrastructure improvements in the LaGorce Neighborhood No. 5 (the “Project”). The Project boundaries are between North Bay Road from 51st Street to Pine Tree Drive, area north of 63rd Street to LaGorce Island and the area to east of Alton Road bounded on the north by the LaGorce Golf Course, on the east by Surprise Waterway and Pine Tree Drive and on the south by Surprise Waterway. The design/build firm (DBF) is to coordinate the work including but not limited to site preparation, earthwork, roadway reconstruction, water main installation and water services relocation, and storm drainage infrastructure installation, street lighting, pedestrian lighting, signalization, landscaping and streetscape improvements. Additionally, the DBF will be responsible for providing architectural, structural engineering, electrical, landscape architecture, construction costs estimating, surveying and geotechnical services for the Project. The City is in the process of incorporating green and blue infrastructure in addition to the traditional grey. Grey infrastructure is considered pipes, pumps, and elevation changes engineered to manage stormwater; green infrastructure is considered trees, wetlands, and vegetative swales intended to mimic the natural water cycle; and blue infrastructure is landscape elements such as ponds, lakes, or water ways intended to store water. This project is intended to be a pilot for incorporation of these concepts to help augment the required design elements.
RFP PROCESS-PHASE I
On July 13, 2016, the City Commission approved the issuance of Request for Proposals (RFP) No. 2016-166-KB Design/Build Services for Right of Way Infrastructure Improvement for Neighborhood No. 5 LaGorce. On July 15, 2016, the RFP was issued. A voluntary pre-proposal conference to provide information to the proposers submitting a response was held on July 27, 2016.
In accordance with Section 287.055 of the Florida Statutes, the RFP provided for a two-step, phased evaluation process. The Phase I selection process, related to the qualifications of the firms through the process outlined in RFP Section 00305, Evaluation Methodology. Only those Proposers deemed to be qualified during Phase I are authorized to proceed to Phase II of the RFP selection process, in which price and detailed technical proposals based on the approved Design Criteria Package (DCP) were considered.
Phase I responses were due and received on August 31, 2016. The City received proposals from the following six (6) firms:
- Bergeron Land Development, Inc.
- David Mancini and Sons, Inc.
- Lanzo Construction Co.
- Layne Heavy Civil
- Ric-Man Construction, Inc.
- Ric-Man International, Inc.
The Evaluation Committee appointed by the City Manager convened on October 13, 2016 to consider proposals received under Phase I. The Committee was provided an overview of the project, information relative to the City’s Cone of Silence Ordinance and the Government Sunshine Law. The Committee was also provided general information on the scope of services, references, and a copy of each proposal. The Committee was instructed to score and rank each proposal pursuant to the evaluation criteria established in the RFP. The evaluation process resulted in the ranking of proposers as indicated in Exhibit “A” attached.
The City’s engineering staff determined that all six (6) responding firms were qualified to perform the work outlined in the RFP. Therefore, as stipulated in the RFP, the City Manager approved for all firms to proceed into Phase II of the solicitation process in which technical proposals and cost are to be considered.
RFP PROCESS – PHASE II
Phase II could not proceed until the Public Works Department engineering team completed the Design Criteria Package (DCP), which is a requirement of Florida law. In view of the large scope for this Project, the DCP divided the work into three segments: Group 1 – South Area, Group 2 – Middle Area, and Group 3 – North Area. Accordingly, upon receipt of the DCP, on March 30, 2017, the Procurement Department issued Phase II of the RFP process to the short-listed proposers. A pre-proposal conference to provide information to the short-listed proposers was held on April 7, 2017. On November 21, 2017, the City received proposals in response to Phase II of the RFP from the following short-listed proposers:
- David Mancini and Sons, Inc.
- Lanzo Construction Co.
- Reynolds Construction LLC
- Ric Man Construction FL, Inc.
- Ric Man International, Inc.
Bergeron Inc., did not submit a proposal for Phase II of the Project. Layne Heavy Civil, who submitted in Phase I, has changed its name to Reynolds Construction LLC.
The Evaluation Committee, appointed by the City Manager via LTC # 011-2018, convened on January 31, 2018 to consider the technical proposals received under Phase II. The Committee was comprised of Eric Arencibia, Capital Projects Coordinator, Capital Improvement Projects Office, City of Miami Beach; Eugene Egemba, Civil Engineer III, Public Works Department, City of Miami Beach; Jack Finglass, Resident, City of Miami Beach; Rodney Knowles, Director, Greenspace Division, Public Works Department, City of Miami Beach; Jose Rivas, Civil Engineer III, Public Works Department, City of Miami Beach; and Margarita Wells, Environmental Resource Manager, Environment and Sustainability, City of Miami Beach.
The Committee was provided an overview of the project, information relative to the City’s Cone of Silence Ordinance and the Government Sunshine Law. The Committee was also provided general information on the scope of services, a copy of each proposal, and engaged in a question and answer session with each proposer. The Committee was instructed to score and rank each proposal pursuant to the evaluation criteria established in the RFP for Phase II. The evaluation process resulted in the ranking of proposers as indicated in Exhibit B, in the following order:
Group I South Area (the area including the Lakeview Subdivision and North Bay Road between Alton Road south of 51st Street)
1st Lanzo Construction Co. of FL.
2nd Ric Man Construction FL Inc.
3rd David Mancini and Sons Inc.
4th Reynolds Construction
5th Ric Man International Inc.
Group 2 Mid Area (the La Gorce Neighborhood from Alton Road to Biscayne Bay along North Bay Road, between 51st Street and 59th Street)
1st Lanzo Construction Co. of FL.
2nd David Mancini and Sons Inc.
3rd Ric Man Construction FL Inc.
4th Reynolds Construction
4th Ric Man International Inc.
Group 3 North Area (the area of La Gorce Neighborhood within the boundaries of 59th Street, La Gorce Island Bridge and 63rd Street, and also 62nd Street between Alton Road and La Gorce Drive)
1st David Mancini and Sons Inc.
2nd Ric Man Construction FL Inc.
3rd Lanzo Construction Co. of FL.
4th Reynolds Construction
4th Ric Man International Inc.
DMSI
According to the information provided by the firm, DMSI’s key partners bring expertise and first-hand knowledge in their respective fields, as well as successfully provided consistent, predictable, and repeatable results on similar D/B projects as a Team. The proposed team for this project depicts the structure and line of authority and communication which is included on the following page; it indicates the Team’s Key members, their intended functions, their responsibilities and percentage of time commitment for this project.
The DMSI/APCTE team considers that a properly prepared, well executed Project Management Plan is essential to the success of this design-build project. From previous experience, they have identified certain principles that have repeatedly proven key to successful Project Management; achieved a fully integrated team with a high standard of accountability and technical excellence; and have provided strict adherence and compliance with the terms of this RFP. Some of these principles include: (1) Establishing clear definitions and authority, (2) Maintain open communication and coordination with all team members and stakeholders, (3) Explicit definition of the work breakdown structure, and the schedule to the Team, and (4) Start with a realistic base line schedule upon which performance can be measured and controlled.
DMSI and APCTE, are experienced and well-known contractors to the City of Miami Beach together have designed and constructed seven (7) Neighborhood Improvement D/B Projects for the City of Miami Beach (Washington Avenue; Lummus; Nautilius West and Orchard Park; Biscayne Point - Biscayne Point & Stillwater Drive; Flamingo - 11th Street; Crespi Boulevard; and Prairie Avenue).
Lanzo
According to the information provided by the DBF, Lanzo has been in this industry for more than 45 years as an underground, structural, and trenchless construction contractor, offering public and private, hard-bid, negotiated, and design-build services. Lanzo is certified General and Underground Contractor, and also have engineering and surveying capabilities.
Lanzo offers the City of Miami Beach a design-build team that combines the experience and local construction know-how of Lanzo, as the DBF, as well as the Contractor with six mainline crews, a number of support crews, and availability that aligns with the contract timing, all located here in Southeast Florida. Wade Trim, as the Lead Design Consultant, is a well-established engineering firm that also offers unparalleled design-build experience that only a large firm can bring, along with the capabilities to understand local challenges and solutions that can come with first-hand experience in working with and alongside local residents and government entities.
The Lanzo/Wade Trim Team will be supported by other local team members experienced in streetscape, stormwater, and water system neighborhood improvements throughout Southeast Florida.
Both firms have completed prior projects for the City. The Public Works Department finds that the prior work has been satisfactory.