The City requires the services of contractors to perform Citywide Demolition Services for the Building Department, primarily for those structures ordered to be demolished by the Unsafe Structures Board. For approximately four (4) years (July 29, 2014 through July 28, 2018), the City has contracted with several contractors to provide these services. The final term of these contracts expires on July 28, 2019.
In order to consider a replacement contract for these services, the City requested proposals from qualified contractors to meet the City’s demolition needs on an as-needed basis. Contractors that are deemed as qualified pursuant to the minimum requirements set forth in this Solicitation shall be placed in a pool for as-needed services. As such, the City, from time to time, will issue Invitations to Quote (ITQ) to the pool of pre-qualified demolition contractors and shall be given an opportunity to quote future projects as they present themselves.
Successful Contractors shall provide all labor, materials, equipment, supplies, insurance, fuels, permits, retirement of utilities and any other items necessary to complete the demolition work, the removal of demolition materials and disposal of materials and related work for these future projects.
The City retains the right to utilize the resulting contracts in a manner that serves the best interests of the City. As such, the City may decide to utilize other procurement methods for future projects when applicable. The resulting contract shall not serve as a guarantee of future work for those contractors deemed to be prequalified pursuant to this solicitation process.
RFQ PROCESS
On June 6, the City Commission approved to issue the City Commission approved to issue the Request for Qualifications (RFQ) No. 2017-183-KB, for Citywide Demolition Services on an as-needed basis. On June 12, 2018, the RFQ was issued. A voluntary pre-proposal conference to provide information to the proposers submitting a response was held on June 28, 2018. RFQ responses were due and received on August 30, 2018. The City received proposals from the following seven (7) firms:
- Camino Real Group Inc. DBA Alpha Wrecking
- Chin Diesel, Inc.
- Cross Environmental Services, Inc.
- Miami Wrecking
- Paragon Construction Unlimited
- The BG Group LLC
- Thunder Demolition
-
On October 18, 2018 the City Manager appointed the Evaluation Committee via LTC # 563-2018. The Evaluation Committee convened on November 6, 2018 to consider proposals received. The committee was comprised of Adrian Avalos, Chief Building Code Compliance Officer, Building Department, City of Miami Beach; Daniel Ceballos, Capital Project Coordinator, Capital Improvement Projects Office, City of Miami Beach; and Antonio Gonzalez, Operations Manager – Plan Review, Building Department, City of Miami Beach.
The Committee was provided an overview of the project, information relative to the City’s Cone of Silence Ordinance and the Government Sunshine Law. The Committee was also provided with general information on the scope of services, a copy of each proposal, and a presentation by each proposing firm. The Committee was instructed to score and rank each proposal pursuant to the evaluation criteria established in the RFQ. The evaluation process resulted in the ranking of proposers as indicated in Attachment A, in the following order:
1st – The BG Group LLC
2nd – Cross Environmental Services, Inc.
3rd – Camino Real Group Inc. DBA Alpha Wrecking
3rd – Chin Diesel, Inc.
5th – Paragon Construction Unlimited
6th – Miami Wrecking
7th – Thunder Demolition
Due to the number of responses, a summary of each top-ranked firm or the firm's proposal is available upon request.