SUBJECT:A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE AMENDMENT NO. 2 TO THE CONSTRUCTION MANAGER AT RISK (CMR) AGREEMENT BETWEEN THE CITY OF MIAMI BEACH, FLORIDA AND BURKHARDT CONSTRUCTION, INC., TO ADD AND REMOVE PRE-CONSTRUCTION SERVICES FOR THE LINCOLN ROAD IMPROVEMENTS PROJECT RESULTING IN A NET INCREASE TO THE CONTRACT PRICE OF $358,145.00, TO BE PAID WITH PREVIOUSLY APPROPRIATED FUNDING.  

BACKGROUND/HISTORY

On February 10, 2016, the City Commission resolved to issue the Request for Qualifications (RFQ) No. 2016-073-KB for Construction Manager at Risk (CMR) For Construction of Lincoln Road District Improvements. The project encompassed Construction Management at Risk services for the construction of the Lincoln Road District Improvements and its related infrastructure inclusive of pre-construction services. Construction phase services shall be included via a Guaranteed Maximum Price (GMP) amendment. The Lincoln Road District Improvements project encompasses the Lincoln Road pedestrian mall between Lennox Avenue and Washington Avenue, and connector streets of Drexel, Pennsylvania, and Meridian Avenues.

 

The proposed design included enhancement of pedestrian walkways and café zones, modifications to the existing planters and water features, landscape and irrigation, storm and sewer drainage, lighting and signalization, performance/multipurpose area at Euclid Avenue, outdoor furniture and outdoor seating areas, crosswalk enhancements, and an artistic gateway folly at Lincoln Road and Washington Avenue with visitor’s guide and wayfinding.

On June 8, 2016 the City Commission adopted Resolution No. 2016-29447 authorizing the Administration to enter into negotiations with the top ranked proposer, Burkhardt Construction. On January 17, 2017, subsequent to negotiations and discussions, a contract for preconstruction services was executed in the amount of $250,190.00.

From August 2016 to March 2017 the pre-construction services were performed in coordination with the designer, James Corner Field Operations (JCFO), The Lincoln Road Business Improvement District (LRBID) and City staff and on March 2017 Burkhardt Construction finalized the Schematic Design Probable Construction Estimate.

On October 28, 2016, following the completion of the schematic design phase and value engineering efforts, the project team presented the design and estimated costs to the Finance and Citywide Projects Committee, which gave direction to the project team to forgo the value engineering options and design to the master plan recommendations.

In January 2018, City Commission adopted Amendment No. 1 to include additional preconstruction phase services for the Project in the lump sum amount of $49,220, to extend the geographic area of the Project, as contemplated in the Lincoln Road Master Plan, to include the area of Lincoln Road from Washington Avenue to Collins Avenue (200-300 Block).

Construction cost estimates prepared using the 50% construction documents indicated a projected construction cost of $65M, resulting in the total project cost being approximately $27M over budget. As a result of the shortfall and extensive discussions, the Lincoln Road Business Improvement District (LRBID) made a commitment to expand the limits of the business improvement district and provide additional funding for programming. On July 31, 2019, pursuant to the Administration’s recommendation and contingent on the commitment from the LRBID, the Mayor and City Commission approved and authorized proceeding with the bidding and construction phases of the project, including a reduction in scope and appropriation of additional funding, bringing the total project budget to $67.6M. The reduction of scope was associated with the omission of the gateway trellis located at the Washington Avenue entrance to Lincoln Road and the omission of the Washington Avenue to Collins Avenue (Lincoln Road 200-300 Blocks) scope.

The design advanced through 90% Construction Documents. Throughout the process, at each design completion milestone, except for the 90% Construction Documents, JCFO and Burkhardt Construction prepared independent cost estimates.

In February 2020, the 90% construction documents were issued by JCFO and the CMR commenced the preparation of the GMP bid packages and finalization of the construction schedule.

On March 12, 2020, the City of Miami Beach declared a State of Emergency in response to the Coronavirus 2019 Pandemic (COVID-19) and announced various emergency measures to mitigate the spread of COVID-19, including the immediate closure of non-essential retail businesses which impacted the commercial businesses along the Lincoln Road corridor.

Market conditions and uncertainty within the construction industry resulted in the Construction Manager At Risk (CMAR), Burkhardt Construction, Inc, advising the City to delay the Guarantee Maximum Price (GMP) process, in order to ensure greater participation by potential bidders. The project team agreed that postponing the bid process was in the best interest of the project.

During the Summer of 2020, City staff and representatives of the LRBID met numerous times to explore and discuss options. In light of the economic impact of the pandemic on the City, the Administration advised the project team and the LRBID that the project budget would be limited to the $52.4 million in funding already available to the project.

On January 13, 2021, the City Commission directed the Administration to reduce the scope of work and keep the project within the originally allocated total budget of approximately $52.4 million, equating to a construction budget of $34 million to $36 million, inclusive of $5.2 million for water/sewer and drainage infrastructure work to be funded separately from alternate funding sources. The reduced scope of work was as follows:

 

• Infrastructure upgrades and improvements at Meridian and Drexel Avenues (water, sanitary sewer & storm drainage)
• Meridian Avenue improvements
• Pedestrianization of Drexel Avenue
• Restoration/repair of fountains and repair of associated equipment
• Restoration of the Lapidus follies
• Upgrade existing light fixtures at existing locations
• Implementation of the concept for the Euclid Avenue oval
• Refurbishing the seating areas along the Lincoln Road corridor
• Refinish the existing piano keys using a more durable traffic coating
• Restoration of aluminum grates of at existing trench drains
• Lincoln Road directional and informational signage package
• A more significant Lincoln Road gateway sign at Washington Avenue, which also serves as a component of the security barrier system
• A matching Lincoln Road gateway sign at Alton Road, which also serves as a component of the security barrier system (this location and scope falls outside the original limits of the project)
• Design and installation of a playground
• Security barrier system, including planters, bollards, furnishings, etc.

 

On December 8, 2021, the City Commission discussed the project and directed the Administration to include $5.2M of RDA funding, previously set aside, allowing the project to utilize the full, available budget of $57.6M, and pursue an agreement with JCFO to revise the design to reflecting the project budget reductions.

ANALYSIS

From February 2021 to May 2022, the City Administration and City staff met numerous times with JCFO to finalize the scope and terms of the amendment to the Professional Service Agreement with JCFO.

On June 22, 2022, the City Commission adopted Resolution 2022-32181 approving Amendment 3 to the Agreement with JCFO for the revision of design for the Lincoln Road Improvements project.

The revised design requires additional pre-construction services for cost estimates at various stages, project scheduling, preparation of bid packages, constructability reviews, and the preparation of a GMP.

City staff requested a proposal from the CMR for additional pre-construction services for the revised design for the Lincoln Road Improvements project, and after numerous discussions, received a proposal from the CMR in the negotiated not-to-exceed amount of $399,520.00 (Exhibit A). The proposal was found to be fair and reasonable.

This Amendment shall also include the removal of scope of work not performed in the original base scope of services in the amount of $41,375.00. The scope removal is associated with bidding, project phasing, scheduling, preparation of GMP and the omission of the 200-300 blocks from the project.

The net value for Amendment No. 2 is $358,145.00 (Exhibit B) which takes into account the removed scope.

The revised total amount of the agreement, including this Amendment No. 2, is $657,555.00.

SUPPORTING SURVEY DATA

N/A

FINANCIAL INFORMATION

N/A
Amount(s)/Account(s):
Amount 1 $ 286,516.00 Account 1 164-0820-069357-00-410-549-00-00-00-29300-RDA Cash Funded CC Project

Amount 2 $ 71,629.00 Account 2 309-0820-069357-00-410-549-00-00-00-29310-RDA Bond CC Project

Total $ 358,145.00

CONCLUSION

The Administration recommends that the Mayor and City Commission approve the resolution.

Applicable Area

South Beach
Is this a "Residents Right to Know" item, pursuant to City Code Section 2-14? Does this item utilize G.O. Bond Funds?
Yes No 

Strategic Connection

Non-Applicable
Legislative Tracking
Capital Improvement Projects

ATTACHMENTS:
Description
Exhibit A - Burkhardt Proposal
Exhibit B - Amendment No. 2 - Lincoln Rd - Burkhardt