Item Coversheet

Resolutions - C7  W




COMMISSION MEMORANDUM

TO:Honorable Mayor and Members of the City Commission 
FROM:Alina T. Hudak, City Manager 
DATE:September  14, 2022
 



SUBJECT:A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE CITY MANAGER AND CITY CLERK TO EXECUTE A UTILITY EASEMENT AGREEMENT IN FAVOR OF FLORIDA POWER & LIGHT, FOR THE PERPETUAL, NON-EXCLUSIVE USE OF AN EASEMENT AREA HAVING APPROXIMATELY 18,381 SQUARE FEET, ALONG A PORTION OF THE PROPERTIES LOCATED AT 1701 CONVENTION CENTER DRIVE AND 1700 WASHINGTON AVENUE, LYING IN A PORTION OF SECTION 35, TOWNSHIP 53 SOUTH, RANGE 42 EAST, FOR THE OPERATION AND MAINTENANCE OF TWO ABOVE GROUND VAULT ROOMS, ASSOCIATED EQUIPMENT AND UNDERGROUND UTILITY FACILITIES, NECESSARY TO SERVE THE ANTICIPATED CONVENTION CENTER HOTEL PROJECT.

RECOMMENDATION

The City Manager recommends approving the proposed utility Easement Agreement in favor of FPL, in the form attached hereto, in order to provide the needed electrical services for the anticipated Convention Center Hotel Project.

BACKGROUND/HISTORY

On July 25, 2018, the Mayor and City Commission adopted Resolution No. 2018-30425, approving a Development and Ground Lease Agreement between the City and MB Mixed Use Investment, LLC for the development of an 800 room convention hotel and related facilities (the “Convention Center Hotel Project”).

 

The proposed Convention Center Hotel Project is set to break ground on an approximate 2.6-acre site on the northeast corner of 17th Street and Convention Center Drive, bounded roughly by the Miami Beach Convention Center to the North, 17th Street to the South, The Fillmore Miami Beach at the Jackie Gleason Theater to the East and Convention Center Drive to the West.

 

As part of the construction phase, Florida Power and Light (“FPL”) will be installing two (2) above ground electrical vault rooms with corresponding underground electrical lines, (the “FPL Facilities”), along a portion of the properties located at 1701 Convention Center Drive and 1700 Washington Avenue, lying in a portion of section 35, Township 53 South, Range 42 East, which will be required to provide electrical service to the proposed Convention Center Hotel Project. It is customary for FPL to require and receive legal authority, pursuant to a perpetual, non-exclusive Easement, to have access to the FPL Facilities for installation, maintenance and repair.

 

Public Works has prepared a Sketch to Accompany Legal Description that describes both the strip of land through which the underground electrical lines run and the location of the vault rooms, a copy of which is attached hereto.

SUPPORTING SURVEY DATA

Results from the 2019 Resident Survey related to perception satisfaction of the City show that 79% of residents were very satisfied/satisfied and rated the City of Miami Beach as a place to live; and 70% were very satisfied/satisfied with the overall image of the City. 

FINANCIAL INFORMATION

No fiscal impact.

CONCLUSION

The City Manager recommends approving the proposed utility Easement Agreement in favor of FPL, in the form attached hereto, in order to provide the needed electrical services for the anticipated Convention Center Hotel Project.
Is this a "Residents Right to Know" item, pursuant to City Code Section 2-14? Does this item utilize G.O. Bond Funds?
Yes No 

Strategic Connection

Environment & Infrastructure - Improve our aging drinking water and sewer infrastructure.
Legislative Tracking
Public Works

ATTACHMENTS:
Description
Agreement - FPL Easement for Convention Center Hotel Project
Sketch and Legal
Resolution