At the October 13, 2021 Commission Meeting, Commissioner Ricky Arriola requested the Finance and Economic Resiliency Committee to review Tyler Tech's performance as a software solution for a number of City processes.
At the May 28, 2014, City Commission meeting, the City Commission authorized a referral to the Finance and City-Wide Projects Committee (the “Committee”) for a discussion on upgrading the City’s current enterprise resource planning (ERP) system, known as Eden, as well as a discussion on Permits Plus, the City’s system for permitting and licensing. The replacement of these systems is a key part of the Administration’s goal of re-engineering core business process to maximize efficiencies and service to constituents, as well as improve internal controls.
The proposed project was comprised of four (4) major project components:
1. Upgrading the City’s current ERP system from Eden to Munis. The City’s version of the Eden software suite had reached end of life.
2. The City’s Permit Plus application, by Accela Government Software, had undergone extensive customization to tailor to the City’s needs. The effort yielded undesirable results and was abandoned. As such, the Administration determined the cost and efficiency benefits of upgrading the current system from Permits Plus to EnerGov, a Tyler product, was determined to be in the best interest of the City.
3. Completing a full business process review (BPR) of all business processes impacted by either Munis or EnerGov, prior to implementation of the new systems.
4. Engaging a dedicated project manager to oversee implementation of the new systems in accordance with the results of the BPR.
At its June 20, 2014, meeting, the Committee considered the Administration’s recommendation that the city replace its ERP system, its system for permitting and licensing, and, prior to implementation of the new systems, conduct a full business process review with the goal of maximizing operational performance, assuring internal controls, and improving service to constituents. The Committee also considered the Administration’s recommendation for project management and implementation services to assure a successful implementation of the project. The Committee has endorsed and recommended that the project be considered by the City Commission. On October 10, 2014, the City Commission approved an agreement with Tyler Technologies, Inc.
Amendment 1 – September 2, 2015
The City’s Steering Committee met on July 16, 2015, and at the advice of Tyler, agreed to consider an amendment to the go-live dates. The committee agreed to perform the system implementation after the City’s audit activities are complete to ensure the availability of subject matter experts (SMEs) of the project. The committee also decided that EnerGov should go live at the same time as Munis Financials to ensure the financial transactions related to permits are contained within a single financial system, instead of spanning both the old and new financial system. As a result, the City and Tyler Technologies recommends amending the “go-live” dates as follows:
Phase 1 – Financials: changed from October 1, 2015, to April 1, 2016.
Phase 2 – EnerGov: changed from December 1, 2015, to April 1, 2016.
Phase 3 – HR/Payroll: changed from July 1, 2016, to January 1, 2017.
Phase 4 – Utility Billing and Revenue: changed from July 1, 2017, to January 1, 2018.
Amendment 2 – October 14, 2015
At its August 13, 2015, and September 24, 2015, meetings, the Steering Committee agreed to recommend to the City Manager that the agreement with Tyler Technologies be amended to allow for the following provisions which will result in a more efficient end product, mitigate any implementation risks and provide the Administration with robust reporting for the oversight and management of operational functions:
1. Software licensing for mobile devices:
Amend the EnerGov iG workforce mobile licensing to purchase a site license that includes unlimited licensing for a total cost of $134,100 plus maintenance of $29,800 per year.
2. Project management:
Amend the dedicated project management services by removing 25% Dedicated Project Manager and 50% Dedicated Project Manager and increasing the Full-Time Project Manager for an additional 12 months for a total of $498,000.
3. Reporting:
Amend the EnerGov Report Development Services from 400 to 1000 hours for a total cost of $170,000.
Amendment 3 – February 10, 2016
At its October 29, 2015, and December 17, 2015, meetings, the Steering Committee made a recommendation to the City Manager to seek to amend the Agreement with Tyler Technologies as follows:
1. EnerGov Reporting Toolkit. The Agreement did not provide the City with an EnerGov Reporting Toolkit license. This toolkit is a piece of software that facilitates report development for the Permitting/Licensing system. This toolkit will allow EnerGov System Administrators to develop custom reports. The Steering Committee recommended purchasing this toolkit, at a total cost of $4,999, plus maintenance of $1,000 per year.
2. End User Training. The Agreement did not provide for End User Training for the Financial System. The end user training approach proposed in the contract was on a “Train the Trainer” basis. After analyzing the training needs of City staff and the limited availability of subject matter experts to train the system’s end users, it was determined that the City would require 26 days of formal training, to be performed by the vendor on City premises. The Steering Committee recommended the addition of End User Training for the Financial System at a cost of $33,150, plus $10,960 in travel costs, for a total cost of $44,110.
3. Professional Services. The Agreement did not provide for Tyler’s professional services to support User Acceptance Testing for the EnerGov Permitting/Licensing system. After analyzing the City’s needs during the User Acceptance testing phase, the Steering Committee recommended the addition of professional services to support City staff during the User Acceptance Testing phase at a cost of $74,800, plus $25,500 in travel costs, for a total cost of $100,300.
Amendment 4 – April 13, 2016
At its February 18, 2016, and March 17, 2016 meetings, the Steering Committee made a recommendation to the City Manager to seek to amend the Agreement with Tyler Technologies as follows, in order to mitigate any implementation risks.
As a result, the City’s ERP Steering Committee recommends adding the following terms to the Agreement:
a. Amend the “Go-Live” dates for Phase 1 – Financials from April 1, 2016, to May 2, 2016.
b. Amend the “Go-Live” dates for Phase 2 – EnerGov from April 1, 2016, to May 2, 2016.
c. Amend the “Go-Live” dates for Phase 3 – HR/Payroll from January 1, 2017, to April 3, 2017
d. Remove 20 implementation days from Munis Inventory
e. Remove 5 implementation days from Munis BMI Collect IT Interface
f. Add 25 implementation days to Phase 1 - Financials
g. Add 895 hours of EnerGov Professional Services, at a cost of $152,150 plus $20,400 in travel costs, for a total cost of $172,550.
Amendment 5 – October 19, 2016
At its May 19, 2016, meeting, the Steering Committee made a recommendation to the City Manager to seek to amend the Agreement with Tyler Technologies to reallocate unused data conversion funds:
- The following unused conversions, totaling $11,250, are hereby removed from the Agreement:
a. Fixed Assets Option 1 – History, at a contract price of $1,750.
b. General Billing Option 1 – Recurring Invoices, at a contract price of $2,500.
c. Inventory Option 1 – Commodity Codes, at a contract price of $1,500.
d. Project Grant Accounting Option 1 – Actuals, at a contract price of $1,750.
e. Project Grant Accounting Option 2 – Budgets, at a contract price of $1,750; and
f. Project Grant Accounting Standard, at a contract price of $2,000.
2. Eight and a half (8.5) Implementation days, totaling $10,838 (at a rate of $1,275 per day), are hereby added to the Agreement
Amendment 6 – January 11, 2017
At its December 15, 2016, meeting, the Steering Committee determined that the quantity of project management services to be provided by Tyler, as set forth in the Agreement, for the implementation are insufficient to complete Phase 3 of the project (the Munis HR/Payroll implementation) and made a recommendation to the City Manager to seek to amend the Agreement with Tyler Technologies. This change results in an overall increase of $62,250.00 for project management services. This item has no impact on the project funding, since the adjustments came from the contingency built into the contract.
Amendment 7 – April 26, 2017
At its March 9, 2017 meeting, the Steering Committee, determined that it was necessary to change the go-live date for Phase 3, HR/Payroll, from April 3, 2017 to May 5, 2017, to allow additional necessary time for the City and Tyler teams to complete system configuration and data conversion, therefore, the quantity of project management services and implementation days to be provided by Tyler, as set forth in the Agreement, for the implementation are insufficient to complete Phase 3, HR/Payroll, and made a recommendation to the City Manager to seek to amend the Agreement with Tyler Technologies as follows:
1. Amend the “Go-Live” dates for Phase 3, HR/Payroll, changed from April 3, 2017 to May 5, 2017.
2. Amend the Project Management Services to be provided by Tyler.
3. Amend the Munis Implementation Days to be provided by Tyler as follow.
These changes resulted in an overall increase of $85,063.00 for project management services and implementation days. This item has no impact on the project funding, since the adjustments came from the contingency built into the contract.
Amendment 8 – August 6, 2018
Both Tyler and The City have now determined that an additional Amendment is required to change the timing of invoicing for the Transparency Portal and Tyler Notify modules; and in consideration of the mutual promises hereinafter contained, Tyler and the City agree as follows:
a. The Tyler Software Transparency Portal is hereby removed from the Agreement. As of such date, Tyler's maintenance, support, and update obligations with respect to such software are terminated.
b. "Invoicing and Payment Policy," is hereby deleted and replaced with the following term:
Subscription Fees: Year one subscription fees for Tyler Notify will be invoiced on January 1, 2020. Subsequent annual subscription fees for Tyler Notify shall be due on January 1st of each year, at Tyler's then-current rates, unless the City's license to Tyler Notify is otherwise terminated, in which the City shall no longer be liable to Tyler for annual subscription fees for Tyler Notify.
Amendment 9 – June 26, 2018
Tyler’s agreement was amended to transition from the included Adobe End User License Agreement ("EULA") for functionality embedded into Tyler's proprietary Tyler Forms product to the DocOrigin software Tyler transitions that provides the same embedded functionality as previously provided by Adobe in the Tyler Forms product.
Amendment 10 – October 21, 2019
Tyler’s agreement was amended as follows:
1. The Bid Management Software is removed-from the Agreement and the City’s license for such software is terminated, as are Tyler's obligations to support, maintain and update such software.
2. The Tyler Notify Software as a Service (SaaS) is hereby removed from the Agreement and the City’s right to use said SaaS is terminated, as are Tyler's obligations to support, maintain, and update such SaaS.
3. In recognition of the maintenance fees paid to Tyler for the Bid Management software, Tyler hereby issues to Client a credit of $24,438.42. The City may apply such credit, at its discretion, to any fees due to Tyler under the Agreement.