COMMISSION MEMORANDUM

TO:Honorable Mayor and Members of the City Commission 
FROM:Jimmy L. Morales, City Manager 
DATE:February  12, 2020
 



SUBJECT:

A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, ACCEPTING THE CITY MANAGER'S RECOMMENDATION, AND APPROVING OPTION 2 FOR THE COMPLETION OF THE ROADWAY CONSTRUCTION OF THE VENETIAN ISLANDS BID PACKAGE 13C, RIGHT-OF-WAY NEIGHBORHOOD IMPROVEMENT PROJECT, UTILIZING FUNDING FROM THE CURRENT PROJECT BUDGET.


RECOMMENDATION

The Administration recommends proceeding with Option 2, utilizing the current funding available in the project budget.

BACKGROUND/HISTORY

On September 9, 2009, pursuant to Request for Qualifications (RFQ) No. 42-08/09, the Mayor and City Commission adopted Resolution No. 2009-27161, approving and authorizing the Mayor and City Clerk to execute a Professional Services Agreement with Schwebke-Shiskin & Associates, Inc. (SS&A) to provide professional services for the design, bid, award, field inspection, and construction administration of the Venetian Island Bid Package 13c, Right-Of-Way Neighborhood Improvement Project.

On March 13th, 2013, pursuant to Invitation to Bid (ITB) No. 49-11/12, for the Right-of-Way Infrastructure Improvement Program – Venetian Islands Bid Package 13C, the City Commission adopted Resolution No. 2013-28163, recommending the award of a construction contract to Lanzo Construction Co. Florida, (Lanzo) in the amount of $11,373,491 including contingency. The scope of work included, site preparation, earthwork, demolition, storm drainage, roadway paving, sidewalks, concrete valley gutters, watermain installation and street lighting on the islands of San Marino, Di Lido and Rivo Alto.

Notice to Proceed (NTP2) for construction was issued effective November 4, 2013.

 

Between February 2014 and January 2016, the City’s Storm Water Management Master Plan was revised, following the recommendations of the Mayor’s Blue-Ribbon Panel on Flooding and Sea Level Rise and of the Flooding Mitigation Committee. As such an enhanced stormwater system criteria was implemented in the project, and revisions to the design were made by SS&A. Revisions included an upgraded stormwater system with no road raising consideration due to the advanced construction stage of the project. The revised design included installation of six new stormwater pump stations within existing easements in the three islands. The installation of the pumps at these proposed locations, was heavily opposed by the residents and required several months of research and negotiations to achieve approval. Consequently, various change orders were issued to Lanzo’s contract, incorporating an upgraded stormwater system with upsize pipes and six new stormwater pump stations with all related equipment and structures, as well as other unforeseen conditions.

 

The contractor encountered unforeseen conditions during excavation activities, unsuitable materials (Muck) was found. The project team determined that the appropriate mitigation was to implement a revised road restoration detail, by using a mixture of the existing and new subgrade materials to be used as a subgrade and installing Geosynthetic Grid (GEOGRID) between the limerock base and the subgrade. This decision was made in consideration of the load capacity restrictions of the Venetian Causeway bridges, implemented in 2014 by Miami-Dade County and FDOT, which affected the allowable weight loads the trucks could haul for subgrade and base materials, reducing the truck load capacity by 40%, making removal and import of large amounts of materials impractical.

Currently, all drainage, watermain, sewer and lighting work has been completed, including all six (6) stormwater pump stations and the restoration of the easements. The remaining contractual scope of work includes the placement of the final lift of asphalt and punch list items. The total construction contract amount to date, including added scope and all other changes is $28,671,330.

ANALYSIS

Installation of the first lift of asphalt began in San Marino Island on May 20, 2015. Within the first month of installation, cracks became evident. Following the installation of the first lift of asphalt on the other two islands, similar cracks developed in varying degrees. Lanzo was notified of the pavement failures and they attempted to correct the issue by applying a crack filler designed for asphalt repairs. They also applied a micro-resurfacing layer on some areas in San Marino Island.

The project did not include raising of the roads. The final road elevations range from 1.06’ to 4.86’ NAVD in San Marino Island, from 1.86’ to 6.16’ NAVD in DiLido Island and from 2.06’ to 3.46’ NAVD in Rivo Alto Island.

During construction of the roadway system, the project’s Resident Project Representative (RPR), SS&A, issued Lanzo more than sixty (60) notices of non-compliance, where more than fifteen of the notices related to improper mixing of subgrade materials, placement of asphalt during wet conditions, and improper handling of backfill material.

SS&A and the City did not accept Lanzo’s attempted asphalt repairs, as they did not address the cause of the premature asphalt cracking. In order to determine the underlying cause, and following SS&A’s recommendations, the City tasked the project’s geotechnical firm, Universal Engineering (Universal), with performing geotechnical testing on the roadway of all three Islands.

Test results common to all three islands, as provided by Universal, indicate that some areas of the roadway have less than the required overall limerock base and stabilized subgrade thickness. Additionally, results in some areas showed the migration of silt into the limerock base, thereby reducing the pavement assembly strength.

At the City’s direction, SS&A analyzed Universal’s geotechnical data and was directed to submit a roadway design with a design life of 20 years. SS&A determined that additional testing was required and hired the professional services of a third-party geotechnical consultant, NV5. NV5 conducted the additional testing and prepared a report that included alternatives ranging from full-depth section replacement, to partial replacement and/or reworking of the existing materials. As a result, SS&A proposed a roadway remediation design which incorporates several assemblies varying from total road reconstruction to simply placing an asphalt overlay. The estimated construction cost is nearly $3 million.

Upon review of all tests reports and recommendations, city staff has identified three options to proceed with the completion of the project:

Option No.1
Proceed with SS&A’s proposed restoration, which includes full-depth section replacement in some areas, partial replacement and/or reworking of the existing materials, in other areas, and provides a pavement design life of 20 years. This option is highly invasive and causes considerable impact to the residents. In addition, it does not address sea level rise impacts to the road base, requiring reconstruction to address the road raising, prior to the end of the design life of the road.

Option No. 2
Potentially milling the existing 1-inch lift of asphalt and overlaying with 2 inches of new asphalt matching the proposed elevation on the original plans. The three islands would be added to the City’s Road Elevation Strategy and Neighborhood Project Prioritization program, for a future roadway improvement project. This option is the least invasive and less impactful to the residents providing an estimated pavement life of several years. The work could be completed within 6 months.

Option No. 3
Proceed with full reconstruction of the roadway, raising the roads to the current or new criteria. This would entail re-design of the stormwater system to meet the determined criteria, in addition to the road raising and harmonization efforts, ultimately resulting in a lengthy construction process and costs in excess of $10 million.

The data obtained indicates that the roadway failure is attributable to the construction deficiencies, and among other things, exacerbated by the interaction of the high ground water table with the roadway assembly. City staff analyzed the test results provided by Universal and NV5 to determine the extent of Lanzo’s liability. Based on that analysis, the estimated cost to reconstruct those areas attributable to construction deficiencies is over $2.6 million. The City is currently withholding $1,361,429 in retainage and approximately $1,355,000 remaining in the contract for work not performed, for a total of approximately $2,716,900. Retainage is a portion of the contract price deliberately withheld until the work is substantially complete to assure the contractor will satisfy its obligations and complete a construction project.

CONCLUSION

The Administration recommends approval of the Resolution.

Applicable Area

South Beach
Is this a Resident Right to Know item? Does this item utilize G.O. Bond Funds?
Yes No 

Strategic Connection

Environment & Infrastructure - Make existing and new government buildings, assets and fleet efficient, sustainable and resilient.
Legislative Tracking
Capital Improvement Projects

ATTACHMENTS:
Description
Resolution